Chapter 4 - Mine Layout
Number Topic Rule of Thumb
4.01 Pit Layout The overall slope (including berms, access roads, and haul roads) of large open pits in good ground will eventually approach the natural angle of repose of broken wall rock (i.e. 38 degrees), except for the last few cuts, which may be steeper.  Source: Jack de la Vergne 
4.02 Pit Layout When hard laterites are mined in an open pit, safe pit slopes may be steeper than calculated by conventional practice (as steep as 50 degrees between haul roads).  Source: Companhia Vale do Rio Doce
4.03 Pit Layout For haul roads in general, 10% is the maximum safe sustained grade.  For particular conditions found at larger operations, the grade has often been determined at 8%.  It is usually safe to exceed the maximum sustained grade over a short distance.  Source: USBM
4.04 Pit Layout The maximum safe grade over a short distance is generally accepted to be 15%.  It may be 12% at larger operations.  Source: Kaufman and Ault
4.05 Pit Layout The maximum safe operating speed on a downhill grade is decreased by 2 km/h for each 1% increase in gradient.  Source: Jack de la Vergne
4.06 Pit Layout Each lane of travel should be wide enough to provide clearance left and right of the widest haul truck in use equal to half the width of the vehicle.  For single lane traffic (one-way), the travel portion of the haul road is twice the width of the design vehicle.  For double lane (two-way), the width of roadway required is 3½ times the width of the widest vehicle.  Source: Association of American State Highway Officials (AASHO)
4.07 Pit Layout To avoid a collision caused by spinout, the width of an open pit haul road should equal the width plus the length of the largest truck plus 15 feet safety distance.  Source: Janet Flinn
4.08 Pit Layout A crushed rock safety berm on a haulage road should be at least as high as the rolling radius of the vehicle tire.  A boulder-faced berm should be of height approximately equal to the height of the tire of the haulage vehicle.  Source: Kaufman and Ault
4.09 Crown Pillar A crown pillar of ore beneath the open pit is usually left in place while underground mining proceeds.  The height of the crown pillar in good ground is typically made equal to the maximum width of stopes to be mined immediately beneath.  When the overburden is too deep, the ore body is not mined by open pit, but a crown pillar is left in place of height the same as if it were.  If the outcrop of the ore body is badly weathered (“oxidized”) or the ore body is cut by major faults, under a body of water or a muskeg swamp - the height of the crown pillar is increased to account for the increased risk.  Source: Ron Haflidson and others
4.10 Mine Entries Small sized deposits may be most economically served by ramp and truck haulage to a vertical depth of as much as 500m (1,600 feet).  Source: Ernie Yuskiw
4.11 Mine Entries A medium-sized deposit, say 4 million (short) tons, may be most economically served by ramp and truck haulage to a vertical depth of 250m (800 feet).  Source: Ernie Yuskiw
4.12 Mine Entries The optimum “changeover” depth from ramp haulage to shaft hoisting is 350m (1,150 feet).  Source: Northcote and Barnes
4.13 Mine Entries In good ground, at production rates less than one million tons per year, truck haulage on a decline (ramp) is a viable alternative to shaft hoisting to depths of at least 300m.  Source: G.G. Northcote
4.14 Mine Entries Western Australia practice suggests a depth of 500m or more may be the appropriate transition depth from decline (ramp) haulage to shaft hoisting.  Source: McCarthy and Livingstone 
4.15 Mine Entries Production rates at operating mines were found to range from 38% to 89% of the estimated truck fleet capacity.  For a proposed operation, 70% is considered to be a reasonable factor for adjusting theoretical estimates to allow for operating constraints.  Source: McCarthy and Livingstone
4.16 Mine Entries Shallow ore bodies mined at over 5,000 tpd are more economically served by belt conveyor transport in a decline entry than haul trucks in a ramp entry.  Source: Al Fernie
4.17 Mine Entries As a rule, a belt conveyor operation is more economical than rail or truck transport when the conveying distance exceeds one kilometer  (3,281 feet).  Source: Heinz Altoff
4.18 Shafts The normal location of the production shaft is near the center of gravity of the shape (in plan view) of the ore body, but offset by 200 feet or more.  Source: Alan O’Hara
4.19 Shafts The first lift for a near vertical ore body should be approximately 2,000 feet.  If the ore body outcrops, the shaft will then be approximately 2,500 feet deep to allow for gravity feed and crown pillar.  If the outcrop is or is planned to be open cut, the measurement should be made from the top of the crown pillar.  If the ore body does not outcrop, the measurement is taken from its apex.  Source: Ron Haflidson
4.20 Shafts The depth of shaft should allow access to 1,800 days mining of ore reserves.  Source: Alan O’Hara
4.21 Shafts For a deep ore body, the production and ventilation shafts are sunk simultaneously and positioned within 100m or so of each other.  Source: D.F.H. Graves
4.22 Underground Layout Footwall drifts for blasthole mining should be offset from the ore by at least 15m (50 feet) in good ground.  Deeper in the mine, the offset should be increased to 23m (75 feet) and for mining at great depth it should be not less than 30m (100 feet).  Source: Jack de la Vergne
4.23 Underground Layout Ore passes should be spaced at intervals not exceeding 500 feet (and waste passes not more than 750 feet) along the footwall drift, when using LHD extraction.  Source: Jack de la Vergne
4.24 Underground Layout The maximum economical tramming distance for a 5 cubic yard capacity LHD is 500 feet, for an 8 cubic yard LHD it is 800 feet.  Source: Len Kitchener
4.25 Underground Layout The amount of pre-production stope development required to bring a mine into production is equal to that required for 125 days of mining.  Source: Alan O’Hara
 
 Print