Chapter 8 - Cost Estimating
Number Topic Rule of Thumb
8.01 Cost of Estimating A detailed estimate for routine, repetitive work (i.e. a long drive on a mine level) may cost as little as 0.5% of the project cost.  On the other hand, it may cost up to 5% to adequately estimate projects involving specialized work, such as underground construction and equipment installation.  Various Sources
8.02 Cost of Feasibility Study The cost of a detailed feasibility study will be in a range from 0.5% to 1.5% of the total estimated project cost.  Source: Frohling and Lewis
8.03 Cost of Feasibility Study The cost of a detailed or “bankable” feasibility study is typically in the range of 2% to 5% of the project, if the costs of additional (in-fill) drilling, assaying, metallurgical testing, geotechnical investigations, etc. are added to the direct and indirect costs of the study itself.  Source: R. S. Frew
8.04 Budget Estimates An allowance (such as 15%) should be specifically determined and added to the contractor’s formal bid price for a mining project to account for contract clauses relating to unavoidable extra work, delays, ground conditions, over-break, grouting, de-watering, claims, and other unforeseen items.  Source: Jack de la Vergne
8.05 Engineering, Procurement, and Construction Management The Engineering, Procurement, and Construction Management (EPCM) cost will be approximately 17% for surface and underground construction and 5% for underground development.  Source: Jack de la Vergne 
8.06 Overbreak The amount of over-break to be estimated against rock for a concrete pour will average approximately 1 foot in every applicable direction, more at brows, lips, and in bad ground.  Source: Jack de la Vergne 
8.07 Overbreak On average, for each 1 cubic yard of concrete measured from the neat lines on drawings, there will be 2 cubic yards required underground, due to overbreak and waste.  Source: Jack de la Vergne
8.08 Haulage The economical tramming distance for a 5 cubic yard capacity LHD is 500 feet and will produce 500 tons per shift, for an 8-yard LHD, it is 800 feet and 800 tons per shift.  Source: Sandy Watson
8.09 Haulage Haulage costs for open pit are at least 40% of the total mining costs; therefore, proximity of the waste dumps to the rim of the pit is of great importance.  Source: Frank Kaeschager
8.10 Miscellaneous Developing countries have labor costs per ton mined equal to approximately 80% of industrialized nations, considering pay scales, mechanization, education, and skill levels.  Source: Kirk Rodgers
8.11 Miscellaneous The installed cost of a long conveyorway is approximately equal to the cost of driving the drift or decline in which it is to be placed.  Source: Jack de la Vergne 
8.12 Miscellaneous The total cost of insurance on a contract-mining job will be approximately 2% of the contract value (including labor).  Source: Darren Small
8.13 Miscellaneous In a trackless mine operating around the clock, there should be 0.8 journeyman mechanic or electrician on the payroll for each major unit of mobile equipment in the underground fleet.  Source: John Gilbert
8.14 Miscellaneous On average, for each cubic yard of concrete measured from the neat lines on drawings, approximately 110 Lbs. of reinforcing steel and 12 square feet of forms will be required.  Source: Jack de la Vergne
8.15 Miscellaneous To estimate shotcrete (dry type) through the machine, add 25% to the neat line take-off to account for surface irregularity (roughness) and overbreak.  Then add rebound at 17-20% from the back and 10% from the wall.  Source: Baz-Dresch and Sherril
8.16 Miscellaneous The overall advance rate of a trackless heading may be increased by 30% and the unit cost decreased by 15% when two headings become available.  Source: Bruce Lang
8.17 Miscellaneous The cost to slash a trackless heading wider while it is being advanced is 80% of the cost of the heading itself, on a volumetric basis.  Source: Bruce Lang
 
 Print